Project category: zeolite runner + RTO
Project location: Langfang, Hebei
Project industry: electronic component manufacturing
Company name: Langfang Foxconn
Process characteristics: spray/paint UV paint
Construction period: October 18, 2019
Completion time: December 15, 2019
Equipment air volume: 250000m³/h
Equipment introduction: cyclone dust removal + cyclone tower + horizontal spray + dry filtration + zeolite runner + RTO process.